TA Blog: New Police Station - project milestones

Below is the TA's report on the status of the new police station construction project. Check back here for regular updates.




11/21/08 Groundbreaking ceremony for the new police station held on Friday, November 21, 2008 at 10 AM at the 500 Great Road building site.


The Permanent Municipal Building Committee voted to award the construction contract to low bidder G&R Construction of Quincy, MA for $4,400,700 for the base bid plus one alternate.


Littleton voters approved a debt exclusion for the new police station on the November 4, 2008 state election ballot by a vote of 2,889 to 2,021.


By a margin of 398 to 69, voters at the October 20, 2008 Special Town Meeting approved borrowing $6.28-million for a new police station


Construction project bid opening - apparent low bidder is G&R Construction of Quincy, MA


State legislation signed placing police station construction debt exclusion ballot question on 11-04-08 state election ballot.



Debt exclusion ballot question for supplemental design funds approved at the May 10, 2008 Annual Town Election by a vote of 802 yes, 497 no


Supplemental design funds of $300,000 were approved at the May 5, 2008 Special Town Meeting




 Return to TA Blog