Date
Milestone
11/13/08
The Permanent Municipal Building Committee voted to award the construction contract to low bidder G&R Construction of Quincy, MA for $4,400,700 for the base bid plus one alternate.
11/4/08
Littleton voters approved a debt exclusion for the new police station on the November 4, 2008 state election ballot by a vote of 2,889 to 2,021.
10/20/08
By a margin of 398 to 69, voters at the October 20, 2008 Special Town Meeting approved borrowing $6.28-million for a new police station.
10/10/08
Construction project bid opening - apparent low bidder is G&R Construction of Quincy, MA
9/16/08
5/10/08
Debt exclusion ballot question for supplemental design funds approved at the May 10, 2008 Annual Town Election by a vote of 802 yes, 497 no
5/5/08
Supplemental design funds of $300,000 were approved at the May 5, 2008 Special Town Meeting